Duane,

This is a symptom of your calendar not being set up far enough out into the future... At least it is for us at V3.5.1.

I'm surprised it's only one part that is giving you the symptom though... So I'm not 100% convinced... Do you have any other parts scheduled out past this part...? What is the End Date on the MPS/MRP screen when you run it...?

Just humor me and examine your Inventory calendar and your manufacturing calendar and make sure they are set up at least through 2005... You always want to have 2 years of future calendar dates set up in all the apps...

Vendor scheduling also exhibits this symptom when the schedule horizon exceeds the available calendar dates...

Let me know...
Thanks.
----Original Message Follows----
From: "Grinstead, Scott" <SAGrinstead@xxxxxxxxxxxxxx>
Reply-To: System 21 Users <system21@xxxxxxxxxxxx>
To: "'System 21 Users'" <system21@xxxxxxxxxxxx>
Subject: RE: [SYSTEM21]   Planning stops in MRP/MPS
Date: Thu, 19 Feb 2004 10:40:01 -0500

Verify that the bill/route has not been affectively ended (if it is an
assembled item then this mean checking both the route that is used to
produce the item and the route where the item is consumed).

Also make sure on the item master that it also has have an item end date
assigned.

I am assuming that the production master detail hasn't been changed to
something that would prevent it from being planned.  One way to do this
would be to assigned the item as a forecast only item and not have a
forecast entered.


Scott Grinstead Sr. Programmer/Analyst Rocky Shoes & Boots



 -----Original Message-----
From:   Johnson, Duane [mailto:djohnson@xxxxxxxxxxxxx]
Sent:   Thursday, February 19, 2004 10:24 AM
To:     'System 21 Users'
Subject:        RE: [SYSTEM21]   Planning stops in MRP/MPS

It's a part that we manufacture.


-----Original Message----- From: system21-bounces@xxxxxxxxxxxx [mailto:system21-bounces@xxxxxxxxxxxx] On Behalf Of Roy Cox Sent: Thursday, February 19, 2004 8:22 AM To: 'System 21 Users' Subject: RE: [SYSTEM21] Planning stops in MRP/MPS

Has the vendor been cancelled?

-----Original Message-----
From: Johnson, Duane [mailto:djohnson@xxxxxxxxxxxxx]
Sent: Thursday, February 19, 2004 9:14 AM
To: 'System 21 Users'
Subject: [SYSTEM21] Planning stops in MRP/MPS

We have ONE part for which all MPS/MRP planning has stopped as of the middle
of April.  We have requirements set up for this part all the way thru the
end of the year.  What might cause this?

        Duane Johnson
        Information Technology Services
        Programming Manager
        Coleman Powermate Inc.
        4970 Airport Rd.
        Kearney, NE 68847
        djohnson@xxxxxxxxxxxxx

_________________________________________________________________
Dream of owning a home? Find out how in the First-time Home Buying Guide. http://special.msn.com/home/firsthome.armx



As an Amazon Associate we earn from qualifying purchases.

This thread ...


Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.