Skip, Weston.
The LT in the Itembl has nothing to do with operation start dates, (sorry
Skip) .
It is calc by PCC . You need to have std hrs in rtn, check your time
basis code. Also, W/C capacities need defined. (double check your Prime
load code, W/C as well)
PCC calc a duration time based on MO qty, Std Hrs( MO op) . and Std
capacity (W/C) .
Hope this helps
Jeff Snyder, CPIM
Mapics Consultant
From: "meyno" <meyno@xxxxxxxxxxxxxxxxxx>
Reply-To: MAPICS ERP System Discussion <mapics-l@xxxxxxxxxxxx>
To: "MAPICS ERP System Discussion" <mapics-l@xxxxxxxxxxxx>
Subject: Re: START TIMES ON MO'S
Date: Wed, 14 Jul 2004 13:23:18 -0400
Lead times need to be added to item balance record with a "M" for lead
time
code
I have a trigger that updates these values when ever maintenance is
performeded on a routing.
----- Original Message -----
From: "Weston Wheat" <wwheat@xxxxxxxxxxxxxx>
To: <mapics-l@xxxxxxxxxxxx>
Sent: Wednesday, July 14, 2004 12:48 PM
Subject: START TIMES ON MO'S
> Hello group.
> Ok, This is going to sound trivial .
> As I have mention, before we are in the process
> of re-aligning our mapics processes. Or I should say
> in the process of matching our bussiness processes to
> mapics. We have allot of work arounds that we want to
> do away with.
> Anyway, we want to take advanage of the MO operations scheduling
> that mapics is capable of , i.e. We want mapics to tell us when to start
a
> operation
> within a MO. I have the in the test environment, gone into Tayloring for
> PCC.
> Have set Backard Scheduling to YES as well as Process Shop activily in
seq.
> to
> Yes. However when I did a test MO, I still got the Start Dates matching
the
> Completion
> Dates. Do we need to load the lead time for the opearations mannally?
> And where would we do that?
>
> Thanks
>
> Weston Wheat
> Information Systems Manager
> Quality Thermistor Inc
> wwheat@xxxxxxxxxxxxxx
> www.thermistor.com
>
> _______________________________________________
> This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
> To post a message email: MAPICS-L@xxxxxxxxxxxx
> To subscribe, unsubscribe, or change list options,
> visit: http://lists.midrange.com/mailman/listinfo/mapics-l
> or email: MAPICS-L-request@xxxxxxxxxxxx
> Before posting, please take a moment to review the archives
> at http://archive.midrange.com/mapics-l.
>
_______________________________________________
This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
To post a message email: MAPICS-L@xxxxxxxxxxxx
To subscribe, unsubscribe, or change list options,
visit: http://lists.midrange.com/mailman/listinfo/mapics-l
or email: MAPICS-L-request@xxxxxxxxxxxx
Before posting, please take a moment to review the archives
at http://archive.midrange.com/mapics-l.
As an Amazon Associate we earn from qualifying purchases.
This mailing list archive is Copyright 1997-2025 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].
Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.