   The LT in the Itembl has nothing to do with operation start dates, (sorry
   Skip) .

   It is calc by PCC . You need to have std hrs in rtn,  check your time
   basis code. Also, W/C capacities need defined. (double check your Prime
   load code, W/C as well) 

    PCC calc a duration time based on MO qty, Std Hrs( MO op) .  and Std
   capacity (W/C) .

    

    Hope this helps

   Jeff Snyder,  CPIM

   Mapics Consultant

   From: "meyno" <meyno@xxxxxxxxxxxxxxxxxx>
   Reply-To: MAPICS ERP System Discussion <mapics-l@xxxxxxxxxxxx>
   To: "MAPICS ERP System Discussion" <mapics-l@xxxxxxxxxxxx>
   Subject: Re: START TIMES ON MO'S
   Date: Wed, 14 Jul 2004 13:23:18 -0400
   Lead times need to be added to item balance record with a "M" for lead
   time
   code
   I have a trigger that updates these values when ever maintenance is
   performeded on a routing.
   ----- Original Message -----
   From: "Weston Wheat" <wwheat@xxxxxxxxxxxxxx>
   To: <mapics-l@xxxxxxxxxxxx>
   Sent: Wednesday, July 14, 2004 12:48 PM
   Subject: START TIMES ON MO'S
   > Hello group.
   > Ok, This is going to sound trivial .
   > As I have mention, before we are in the process
   > of re-aligning our mapics processes. Or I should say
   > in the process of matching our bussiness processes to
   > mapics. We have allot of work arounds that we want to
   > do away with.
   > Anyway, we want to take advanage of the MO operations scheduling
   > that mapics is capable of , i.e. We want mapics to tell us when to start
   a
   > operation
   > within a MO. I have the in the test environment, gone into Tayloring for
   > PCC.
   > Have set Backard Scheduling to YES as well as Process Shop activily in
   seq.
   > to
   > Yes. However when I did a test MO, I still got the Start Dates matching
   the
   > Completion
   > Dates. Do we need to load the lead time for the opearations mannally?
   > And where would we do that?
   >
   > Thanks
   >
   > Weston Wheat
   > Information Systems Manager
   > Quality Thermistor Inc
   > wwheat@xxxxxxxxxxxxxx
   > www.thermistor.com
   >
   > _______________________________________________
   > This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
   > To post a message email: MAPICS-L@xxxxxxxxxxxx
   > To subscribe, unsubscribe, or change list options,
   > visit: http://lists.midrange.com/mailman/listinfo/mapics-l
   > or email: MAPICS-L-request@xxxxxxxxxxxx
   > Before posting, please take a moment to review the archives
   > at http://archive.midrange.com/mapics-l.
   >
   _______________________________________________
   This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
   To post a message email: MAPICS-L@xxxxxxxxxxxx
   To subscribe, unsubscribe, or change list options,
   visit: http://lists.midrange.com/mailman/listinfo/mapics-l
   or email: MAPICS-L-request@xxxxxxxxxxxx
   Before posting, please take a moment to review the archives
   at http://archive.midrange.com/mapics-l.

As an Amazon Associate we earn from qualifying purchases.

This thread ...

Follow-Ups:

Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.