Skip, Just to clarify. STD LT does affect, (offsets) the MO start date from the due date , if left blank during create. I believe the question was about 'operation' start dates, which is not affected by itembl STD LT. PCC also will calc the 'scheduled start date' (if backward scheduling) using the before mentioned run times, setup, W/C , etc. A comparison is performed to the original MO start date, and PCC will claculate days off schedule and critical ratio. Lets you know which MOs are potentially in danger of being late. Jeff Snyder, CPIM Mapics Consultant ps: Hey Skip; (footnote) Play any pool lately ? From: "meyno" <meyno@xxxxxxxxxxxxxxxxxx> Reply-To: MAPICS ERP System Discussion <mapics-l@xxxxxxxxxxxx> To: "MAPICS ERP System Discussion" <mapics-l@xxxxxxxxxxxx> Subject: Re: START TIMES ON MO'S Date: Wed, 14 Jul 2004 16:19:20 -0400 LT time does matter with the MO start Date. ----- Original Message ----- From: "Jeff Snyder" <jeffreygsnyder@xxxxxxxxxxx> To: <mapics-l@xxxxxxxxxxxx> Sent: Wednesday, July 14, 2004 1:37 PM Subject: Re: START TIMES ON MO'S > Skip, Weston. > > > > The LT in the Itembl has nothing to do with operation start dates, (sorry > Skip) . > > It is calc by PCC . You need to have std hrs in rtn, check your time > basis code. Also, W/C capacities need defined. (double check your Prime > load code, W/C as well) > > PCC calc a duration time based on MO qty, Std Hrs( MO op) . and Std > capacity (W/C) . > > > > Hope this helps > > Jeff Snyder, CPIM > > Mapics Consultant > > From: "meyno" <meyno@xxxxxxxxxxxxxxxxxx> > Reply-To: MAPICS ERP System Discussion <mapics-l@xxxxxxxxxxxx> > To: "MAPICS ERP System Discussion" <mapics-l@xxxxxxxxxxxx> > Subject: Re: START TIMES ON MO'S > Date: Wed, 14 Jul 2004 13:23:18 -0400 > Lead times need to be added to item balance record with a "M" for lead > time > code > I have a trigger that updates these values when ever maintenance is > performeded on a routing. > ----- Original Message ----- > From: "Weston Wheat" <wwheat@xxxxxxxxxxxxxx> > To: <mapics-l@xxxxxxxxxxxx> > Sent: Wednesday, July 14, 2004 12:48 PM > Subject: START TIMES ON MO'S > > Hello group. > > Ok, This is going to sound trivial . > > As I have mention, before we are in the process > > of re-aligning our mapics processes. Or I should say > > in the process of matching our bussiness processes to > > mapics. We have allot of work arounds that we want to > > do away with. > > Anyway, we want to take advanage of the MO operations scheduling > > that mapics is capable of , i.e. We want mapics to tell us when to start > a > > operation > > within a MO. I have the in the test environment, gone into Tayloring for > > PCC. > > Have set Backard Scheduling to YES as well as Process Shop activily in > seq. > > to > > Yes. However when I did a test MO, I still got the Start Dates matching > the > > Completion > > Dates. Do we need to load the lead time for the opearations mannally? > > And where would we do that? > > > > Thanks > > > > Weston Wheat > > Information Systems Manager > > Quality Thermistor Inc > > wwheat@xxxxxxxxxxxxxx > > www.thermistor.com > > > > _______________________________________________ > > This is the MAPICS ERP System Discussion (MAPICS-L) mailing list > > To post a message email: MAPICS-L@xxxxxxxxxxxx > > To subscribe, unsubscribe, or change list options, > > visit: http://lists.midrange.com/mailman/listinfo/mapics-l > > or email: MAPICS-L-request@xxxxxxxxxxxx > > Before posting, please take a moment to review the archives > > at http://archive.midrange.com/mapics-l. > > > _______________________________________________ > This is the MAPICS ERP System Discussion (MAPICS-L) mailing list > To post a message email: MAPICS-L@xxxxxxxxxxxx > To subscribe, unsubscribe, or change list options, > visit: http://lists.midrange.com/mailman/listinfo/mapics-l > or email: MAPICS-L-request@xxxxxxxxxxxx > Before posting, please take a moment to review the archives > at http://archive.midrange.com/mapics-l. > _______________________________________________ > This is the MAPICS ERP System Discussion (MAPICS-L) mailing list > To post a message email: MAPICS-L@xxxxxxxxxxxx > To subscribe, unsubscribe, or change list options, > visit: http://lists.midrange.com/mailman/listinfo/mapics-l > or email: MAPICS-L-request@xxxxxxxxxxxx > Before posting, please take a moment to review the archives > at http://archive.midrange.com/mapics-l. > _______________________________________________ This is the MAPICS ERP System Discussion (MAPICS-L) mailing list To post a message email: MAPICS-L@xxxxxxxxxxxx To subscribe, unsubscribe, or change list options, visit: http://lists.midrange.com/mailman/listinfo/mapics-l or email: MAPICS-L-request@xxxxxxxxxxxx Before posting, please take a moment to review the archives at http://archive.midrange.com/mapics-l.
As an Amazon Associate we earn from qualifying purchases.
This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].
Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.