Weston, First of all, you may not want to process operations in sequence because this forces you to complete operations in sequence. If you have multiple operations open at the same time, they have to be completed in the sequence they are entered even if they are actually completed in some other sequence. This has nothing to do with how the system schedules the order. You need to define your operation times in the Routing file and the queue times in the Work Center (Production Facility) file. When you open a mfg order, say "yes" to routings and the system will calculate operation lead times based on the Routing and Work Center files. Be aware that lead times are in days and that if your standard times are less than one day, the total lead time could be less than a day. Make sure that the time basis codes in the routing file are correct so that the lead times by operation are calculated correctly. Backward scheduling should be okay, realizing that the system could calculate a start prior to the current date. I hope this helps. There is a CD for MAPICS/XA that contains all the manuals for the system. There is a Rel. 4 version and a Rel.6 version. They are in PDF format and are an excellent resource for determining what MAPICS is doing and how to set up your system to do what you want. David -----Original Message----- From: Weston Wheat [mailto:wwheat@xxxxxxxxxxxxxx] Sent: Wednesday, July 14, 2004 11:48 AM To: mapics-l@xxxxxxxxxxxx Subject: START TIMES ON MO'S Hello group. Ok, This is going to sound trivial . As I have mention, before we are in the process of re-aligning our mapics processes. Or I should say in the process of matching our bussiness processes to mapics. We have allot of work arounds that we want to do away with. Anyway, we want to take advanage of the MO operations scheduling that mapics is capable of , i.e. We want mapics to tell us when to start a operation within a MO. I have the in the test environment, gone into Tayloring for PCC. Have set Backard Scheduling to YES as well as Process Shop activily in seq. to Yes. However when I did a test MO, I still got the Start Dates matching the Completion Dates. Do we need to load the lead time for the opearations mannally? And where would we do that? Thanks Weston Wheat Information Systems Manager Quality Thermistor Inc wwheat@xxxxxxxxxxxxxx www.thermistor.com _______________________________________________ This is the MAPICS ERP System Discussion (MAPICS-L) mailing list To post a message email: MAPICS-L@xxxxxxxxxxxx To subscribe, unsubscribe, or change list options, visit: http://lists.midrange.com/mailman/listinfo/mapics-l or email: MAPICS-L-request@xxxxxxxxxxxx Before posting, please take a moment to review the archives at http://archive.midrange.com/mapics-l.
As an Amazon Associate we earn from qualifying purchases.
This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].
Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.