Hmmm, you have my curiosity on this one... Possibly a system flag issue (in SYS800-10 screen, is 'Run MPS/MRP by Facility' set on?). Or possibly something with the items themselves, (what warehouse is the ' Item Stocking Warehouse' in INV100?). Lastly, do you see CIC records for these parts for facility 92? If not, maybe try creating one thru MRP140...
Nelson Stud Welding, Inc.
440-329-0400
A DONCASTERS Group Limited Company
-----Original Message-----
From: bpcs-l-bounces@xxxxxxxxxxxx [mailto:bpcs-l-bounces@xxxxxxxxxxxx] On Behalf Of Larenzo Alexander
Sent: Wednesday, September 21, 2011 10:14 AM
To: BPCS ERP System
Subject: Re: [BPCS-L] Planned Orders Not Showing but in KFP
Yep, Facility is set to 92 in warehouse maintenance for warehouse AC. The Facility 92 is connected to warehouse AC in facility maintenance. An for facility 92 we don't run both MRP500 & MRP600. We usually only run MRP600 but I thought that may be the problem so I tried a couple of times by running both MRP500 & MRP600 against this facility 92 but stilll no luck.
Thanks
Warehouse Mainteance:
Allocatable Whse? Y (Y/N)
Nettable MRP Whse? Y (Y/N)
Output Queue BPCSOUTQ
Default Company 1 + (G/L only)
Cost Material? N (Y/N)
Forecast Flag? N (Y/N)
Facility 92 +
Hazardous Material 0 (0=No, 1=Yes)
Allocation Required 0 (0=No, 1=Yes)
Zone/Pick Sequence 0 (0=Alpha Search
Faciltity Maintenance:
Mass Release Warehouse AC +
Default Stocking Warehouse AC +
Facility Wide Allocations/Backflushes 0 (1=Yes 0=No)
MRP Planning Start Date 1/01/11
From: DeeDee Virgei <DeeDee.Virgei@xxxxxxxxxxxxxx>
To: BPCS ERP System <bpcs-l@xxxxxxxxxxxx>
Sent: Wednesday, September 21, 2011 9:43 AM
Subject: Re: [BPCS-L] Planned Orders Not Showing but in KFP
Hi Larenzo,
Is the facility set to '92' on Whse AC (under the 'Forecast Flag?' setting below)? Also, do you run both MRP500 and MRP600? Just some more thoughts...
Nelson Stud Welding, Inc.
440-329-0400
A DONCASTERS Group Limited Company
The information contained herein, including any attachments, is confidential and is intended for the exclusive use of the addressee. Any dissemination or use of this information by a person other than the intended recipient is unauthorized and may be illegal. If you have received this e-mail in error, please notify the sender immediately by reply e-mail and destroy all copies.
-----Original Message-----
From: bpcs-l-bounces@xxxxxxxxxxxx [mailto:bpcs-l-bounces@xxxxxxxxxxxx] On Behalf Of Larenzo Alexander
Sent: Wednesday, September 21, 2011 9:24 AM
To: BPCS ERP System
Subject: Re: [BPCS-L] Planned Orders Not Showing but in KFP
Ok, Just checked the warehouse settings and the warehouse isn't non-nettable or non-allocatable.
Warehouse AC Accessories
Allocatable Whse? Y (Y/N)
Nettable MRP Whse? Y (Y/N)
Output Queue BPCSOUTQ
Default Company 1 + (G/L only)
Cost Material? N (Y/N)
Forecast Flag? N (Y/N)
Thanks
From: Bryce Martin <BMartin@xxxxxxxxxxxx>
To: BPCS ERP System <bpcs-l@xxxxxxxxxxxx>
Sent: Wednesday, September 21, 2011 9:08 AM
Subject: Re: [BPCS-L] Planned Orders Not Showing but in KFP
Make sure the warehouse is not set up at non-nettable or non-allocatable.
Thanks
Bryce Martin
Programmer/Analyst I
570-546-4777
DeeDee Virgei <DeeDee.Virgei@xxxxxxxxxxxxxx>
Sent by: bpcs-l-bounces@xxxxxxxxxxxx
09/21/2011 08:45 AM
Please respond to
BPCS ERP System <bpcs-l@xxxxxxxxxxxx>
To
BPCS ERP System <bpcs-l@xxxxxxxxxxxx>
cc
Subject
Re: [BPCS-L] Planned Orders Not Showing but in KFP
Hi Peter,
Is the shop calendar setup for that facility (FSC)? I know the MRP
programs use it, although not stated as mandatory...
Nelson Stud Welding, Inc.
440-329-0400
A DONCASTERS Group Limited Company
-----Original Message-----
From: bpcs-l-bounces@xxxxxxxxxxxx [mailto:bpcs-l-bounces@xxxxxxxxxxxx] On
Behalf Of Larenzo Alexander
Sent: Wednesday, September 21, 2011 7:56 AM
To: BPCS ERP System
Subject: Re: [BPCS-L] Planned Orders Not Showing but in KFP
Hello,
I just double checked the KFP records and the warehouse is 'AC' and
facility is '92' and the due dates are 9/20/2011. An in MRP Maintenance
(MRP510) the customer order requirements arent showing either. It is a new
warehouse and facility we just set up and this is the first time the users
ran MRP against it. I maybe missing something in the setup process but
everything looks good behind the scenes but not showing on the planning
screens.
Thanks
From: Peter Heeren <pheeren@xxxxxxxxxxx>
To: BPCS ERP System <bpcs-l@xxxxxxxxxxxx>
Sent: Wednesday, September 21, 2011 1:49 AM
Subject: Re: [BPCS-L] Planned Orders Not Showing but in KFP
Hi Larenzo
Check KFP for records for the facility, wharehouse, item and see if
there are records wit the same duedate
Kind regards,
Peter Heeren
From: Larenzo Alexander <larenzo_alexander@xxxxxxxxx>
To: BPCS Forum Post <bpcs-l@xxxxxxxxxxxx>
Date: 20-09-11 21:16
Subject: [BPCS-L] Planned Orders Not Showing but in KFP
Sent by: bpcs-l-bounces@xxxxxxxxxxxx
I see planned orders in the KFP file for facility '92' warehouse 'AC' but
they aren't showing in MRP Maintenace (MRP510) or Planning Pegging/Inquiry
(MRP300) but they do show in our PO Consolidation/Release Mainteance
(PUR640B).
The facility and warehouse code appears to be set up correctly and we
performed MRP explosion several times against facility 92 to make sure
that wasnt the problem.
Any idea what I may need to check like a Facility reset or MRP reset or
something?
We 're running BPCS 6.1
Thanks
As an Amazon Associate we earn from qualifying purchases.
This thread ...
Re: Planned Orders Not Showing but in KFP, (continued)
This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact
[javascript protected email address].
Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.