Eric,
The only thing that comes from production to DEV/Test or QA LPAR's is data
(which have a a home grown extraction/load process so we can bring across
subsets of data). IBM PTF's are usually loaded on the DEV machine first,
then QA then rolled out to prod.
-----Original Message-----
From: elehti@xxxxxxxxxxxxxxxxxx
Sent: Monday, October 08, 2012 9:21 AM
To: midrange-l@xxxxxxxxxxxx
Subject: RE: PTF Best Practice? apply to separate LPAR first,or to a
non-production machine?
Crispin, what save/restore/copy process do you use to populate the
various LPARs from production?
We do, but we have a DEV/Test, QA, and multiple production LPARs
so...Crispin.