The general interpretation of the SC module is that it's not recommended by
JBA manufacturing consultants (names withheld).  We circumnavigate the
process as follows:

        - An O/S item number is created in JBA to represent an Outside
Process.
        - The O/S item number is vendor scheduled identical to a Raw
Material.
        - The Vendor Schedule is your "scheduled" quantity to ship to O/S
vendor.
        - Stockroom "OP" is created simply to separate and "easily identify
Outside Processing      balances (or imbalances)".
        - Unprocessed "Raw Material" for O/S are MANUALLY "Stock
Transferred" from 03 (Main) to OP       (same value).
        - The O/S item is received into Stockroom "OP" (item to be 3-way
matched).
        - Both O/S item and Raw Material (transferred from Main SR) are
backflushed (issued) out        of stockroom "OP"  
        - O/S reconciliation is simplified by stockroom: Raw Material Issued
& Completed O/S         Received, less Gross Manufactured @ Standard
(technically, each item in OP stockroom         should be zero excluding
"In-process Inventory" and unplanned O/S scrap).
        - The OP stockroom will have to be scrutinized daily like any other
inventory, O/S vendor   will have to provide "scrapped" items (to be
scrapped in the Inventory system as a "S"       transaction - AFI rule
required), and Physical Inventory will NOT have to include O/S  items.     


-----Original Message-----
From: Monica.Moloney@olympus.ie [mailto:Monica.Moloney@olympus.ie]
Sent: Thursday, August 17, 2000 10:27 AM
To: JBAUSERS-L@midrange.com
Subject: Subcontractors



Hi all,

Does anyone use the Subcontractor module  (/MKS),  and I would like to know
of your experience's with it.

We need to be able to :

Set up a work order, we will perform the first and second operation say, ie
print and send all packaging, and then we need to send them out to a
subcontractor, who will fill and pack the product,  and then send the
product back to us in Kits(packs of 6), ie we will send out 6,000 labels,
and they will send us back 990 kits.


To save costs, we normally send out 20,000 labels at a time, Can the
Subcontractor module take care of this ?



Regards

Monica Moloney


+---
| This is the JBA Software Users Mailing List!
| To submit a new message send your mail to JBAUSERS-L@midrange.com.
| To subscribe to this list send email to JBAUSERS-L-SUB@midrange.com.
| To unsubscribe from this list send email to JBAUSERS-L-UNSUB@midrange.com.
| Questions should be directed to the list owner: doug333@aol.com.
+---
+---
| This is the JBA Software Users Mailing List!
| To submit a new message send your mail to JBAUSERS-L@midrange.com.
| To subscribe to this list send email to JBAUSERS-L-SUB@midrange.com.
| To unsubscribe from this list send email to JBAUSERS-L-UNSUB@midrange.com.
| Questions should be directed to the list owner: doug333@aol.com.
+---

As an Amazon Associate we earn from qualifying purchases.

This thread ...


Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.