That would work as well if the orders and material were turned quickly. The
reason why we don't do that is b/c our outsource companies may hold our
component inventory for quite some time. To save confusion, we don't want
to show these components in our inventory at our facility. If a MO is
executed, there needs to be component stock in the inventory to deplete and
avoid negative quantities.
Todd Ivy
TYMCO, Inc.
225 E. Industrial Blvd
Waco, Tx 76705
T:(254) 799-5546 Ext:389
F:(254) 799-2722
www.tymco.com <
http://www.tymco.com>
-----Original Message-----
From: mapics-l-bounces@xxxxxxxxxxxx
[mailto:mapics-l-bounces@xxxxxxxxxxxx]On Behalf Of Tom E Stieger
Sent: Wednesday, November 18, 2009 1:39 PM
To: mapics-l@xxxxxxxxxxxx
Subject: Re: [MAPICS-L] Contract FAB
Why not create an item for the outsource contract work?
The finished item can then have an MO created for it with a bill of material
including all the components needed and the outsource service item. Then
the finished goods item will have the cost of the components and the service
to put them together.
-Tom Stieger
Engineer
California Fine Wire
-----Original Message-----
From: mapics-l-bounces@xxxxxxxxxxxx [mailto:mapics-l-bounces@xxxxxxxxxxxx]
On Behalf Of Todd Ivy
Sent: Wednesday, November 18, 2009 11:21 AM
To: MAPICS ERP System Discussion
Subject: Re: [MAPICS-L] Contract FAB
Kevin,
We manufacture most of our "manufacturable" parts in house. Although, for
some parts it makes more sense to outsource. In this case, we manufacture
all of the components in house through Manufacturing Work Orders, gather
parts and a parts list, and send parts to outsource company along with a PO.
When components are sent out, we execute a misc issue (IS) for all of the
components leaving our facility. Then the finished products are eventually
received back to our stock as a completed weldment on a PO.
This is theoretical. It works well if all persons involved care enough to
play along. If anyone has better ideas, I would be interested as well.
Todd Ivy
TYMCO, Inc.
225 E. Industrial Blvd
Waco, Tx 76705
T:(254) 799-5546 Ext:389
F:(254) 799-2722
www.tymco.com <
http://www.tymco.com>
-----Original Message-----
From: mapics-l-bounces@xxxxxxxxxxxx
[mailto:mapics-l-bounces@xxxxxxxxxxxx]On Behalf Of Kevin Fox
Sent: Wednesday, November 18, 2009 1:09 PM
To: 'MAPICS ERP System Discussion'
Subject: [MAPICS-L] Contract FAB
All,
I is common business practice to sub-contract board fabrication. It is also
common business practice to supply some or all of the components for the
fab(less) shop.
I'd like to know how you are handling such an issue. Basically, how do you
supply a vendor components with a PO?
Thanks in advance for your expertise.
Kevin Fox
_______________________________________________
This is the MAPICS ERP System Discussion (MAPICS-L) mailing list To post a
message email: MAPICS-L@xxxxxxxxxxxx To subscribe, unsubscribe, or change
list options,
visit:
http://lists.midrange.com/mailman/listinfo/mapics-l
or email: MAPICS-L-request@xxxxxxxxxxxx
Before posting, please take a moment to review the archives at
http://archive.midrange.com/mapics-l.
_______________________________________________
This is the MAPICS ERP System Discussion (MAPICS-L) mailing list To post a
message email: MAPICS-L@xxxxxxxxxxxx To subscribe, unsubscribe, or change
list options,
visit:
http://lists.midrange.com/mailman/listinfo/mapics-l
or email: MAPICS-L-request@xxxxxxxxxxxx
Before posting, please take a moment to review the archives at
http://archive.midrange.com/mapics-l.
_______________________________________________
This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
To post a message email: MAPICS-L@xxxxxxxxxxxx
To subscribe, unsubscribe, or change list options,
visit:
http://lists.midrange.com/mailman/listinfo/mapics-l
or email: MAPICS-L-request@xxxxxxxxxxxx
Before posting, please take a moment to review the archives
at
http://archive.midrange.com/mapics-l.
As an Amazon Associate we earn from qualifying purchases.