I think it is coming from somewhere else as I can see that nothing is
entered at run time, also, the dates are different on some items for the
same model which I why I thought the purchase lead time (field LTIW71) was
the culprit. But it has something to do with the "additional parameters"
where you can specify "Use Item Time Fence" and "Use Item End Date".
When those parameters are set to "1" (yes) then I can see the dates being
affected. So my question is, where is the "Item Time Fence" kept ?
Anybody.....
TIA.
Jim.
-----Original Message-----
From: system21-bounces@xxxxxxxxxxxx [mailto:system21-bounces@xxxxxxxxxxxx]
On Behalf Of rick.allen@xxxxxxxxxxx
Sent: Tuesday, January 15, 2008 6:50 PM
To: System 21 Users
Subject: Re: [SYSTEM21] MRP Time Fence.
Hi Jim
MSP71 is populated by the values entered when you start an MRP run either
manually (MR002) or via Auto run parameters (for MM submission in Aurora).
These values are also output at start of run to the MR003PT report.
Start Date = run date - overdue days as entered on the screen
Time Fence date = run date + time fence days as entered on the screen
End Date = date as entered ( or run date + entered days for Auto Run)
Not sure about Forecast time fence as we don't use it.
BR
Rick Allen
IT Manager
IT
Sandvik Mining and Construction Australia
Office: +61 (0)2 4985 2622
Mobile: +61 (0)419 494 705
Fax: +61 (0)2 4985 2626
Mailto:rick.allen@xxxxxxxxxxx
http://www.sandvik.com
This e-mail is confidential and it is intended only for the addressees.
Any review, dissemination, distribution, or copying of this message by
persons or entities other than the intended recipient is prohibited. If
you have received this e-mail in error, kindly notify us immediately by
telephone or e-mail and delete the message from your system. The sender
does not accept liability for any errors or omissions in the contents of
this message which may arise as a result of the e-mail transmission.
"Jim Kerr" <JKerr@xxxxxxxxxxxxxxxxxxxxxx>
Sent by: system21-bounces@xxxxxxxxxxxx
16/01/2008 12:12 PM
Please respond to
System 21 Users <system21@xxxxxxxxxxxx>
To
"'System 21 Users'" <system21@xxxxxxxxxxxx>
cc
Subject
[SYSTEM21] MRP Time Fence.
On the MRP Inquiry summary screen (MR050), there are 4 dates displayed at
the top of the screen;
Start 5/11/07 Time Fence 6/26/09 F/C Time Fence 1/16/08 End
6/26/09
I am interested in knowing what creates the value for the "Time Fence" and
"End" dates. These fields appear to be taken from file MSP71, fields
PSTF71 and PSED71 respectively. I also note that there is a value in
field
LTIW71 (Purchasing lead time) of 420, does this get used in calculating
the
time fence and end date and if so, where is that value coming from ?
TIA,
Jim.
_______________________________________________
This is the System 21 Users (SYSTEM21) mailing list
To post a message email: SYSTEM21@xxxxxxxxxxxx
To subscribe, unsubscribe, or change list options,
visit:
http://lists.midrange.com/mailman/listinfo/system21
or email: SYSTEM21-request@xxxxxxxxxxxx
Before posting, please take a moment to review the archives
at
http://archive.midrange.com/system21.
_______________________________________________
This is the System 21 Users (SYSTEM21) mailing list
To post a message email: SYSTEM21@xxxxxxxxxxxx
To subscribe, unsubscribe, or change list options,
visit:
http://lists.midrange.com/mailman/listinfo/system21
or email: SYSTEM21-request@xxxxxxxxxxxx
Before posting, please take a moment to review the archives
at
http://archive.midrange.com/system21.
As an Amazon Associate we earn from qualifying purchases.