We are about to begin the process of testing of a 4 week firm time fence in our test environment for MRP/MPS. However, I'm not sure on the value that needs to be entered on /MRP 11, "Time Fence Days". Could anybody tell me if that field is based on a 5 day work week or a 7 day work week? Thanks for your help, Greg Greg Page Sr. Business Systems Analyst Strattec Security Corp. Ph: 414-247-3634 Fx: 414-247-3329
As an Amazon Associate we earn from qualifying purchases.
This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].