Thank you for the reply Vojtech. Appreciate the information and insight.
Regards,Laura
Laura A. UbelhorPresidentConsultech Services, Inc.www.consultechservicesinc.com
phone 248-701-7410
On Sunday, May 4, 2025 at 01:15:18 PM EDT, Vojtěch Mrázek <vojtech.mrazek@xxxxxxx> wrote:
Hello Laura,
first create your simulation site in Power-Link - use the function Copy to copy your production site to simulation site.
Then make all desired changes (change facility rates, overhead rates etc.). You can use SQL or RPG program to modify your rates in simulation site (be carefull as usually :o)
The submit Costing for your simulation site.
Create a query to compare costs in production site and simulation site.
I usually delete the simulation site immediately, because it is confusing for Engineering to have two records for each item, faclity, BOM, routing.
Works fine.
Vojtech Mrazek
________________________________
Od: MAPICS-L <mapics-l-bounces@xxxxxxxxxxxxxxxxxx> za uživatele ubelhor@xxxxxxxxxxxxx <ubelhor@xxxxxxxxxxxxx>
Odesláno: pátek 2. května 2025 17:53
Komu: MAPICS ERP System Discussion <mapics-l@xxxxxxxxxxxxxxxxxx>
Předmět: [MAPICS-L] set up costing simulation in Powerlink
Hello:
Has anyone successfully set up costing simulation in Powerlink? There is a KB and documentation referencing costing simulation but not very detailed instructions. We have fiddled but it simply just does not work.
Can you share any advice or recommendations please.
Regards,Laura
Laura A. UbelhorPresidentConsultech Services, Inc.www.consultechservicesinc.com
phone 248-701-7410
--
This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
To post a message email: MAPICS-L@xxxxxxxxxxxxxxxxxx
To subscribe, unsubscribe, or change list options,
visit:
https://lists.midrange.com/mailman/listinfo/mapics-l
or email: MAPICS-L-request@xxxxxxxxxxxxxxxxxx
Before posting, please take a moment to review the archives
at
https://archive.midrange.com/mapics-l.
As an Amazon Associate we earn from qualifying purchases.