That audit job requirement has been around since we started running OE&I!!! Waaaaaay back - we just scheduled the audits every night at end of day and again anytime pre-MRP processing. And we still got caught in CO maintenance that happened during the day.
One way we discovered that prevented the problem was to completely cancel the order out of the system and re-enter it. Drastic solution, but we didn't have allocation/availability issues if we did that. We could get away with that since we had a very easy-to-use offline order entry process.
Isn't YouTube great? I'd be worried though, if I was Charley.... with his company they probably have a really high-speed turbocharged flogger available! (Cool video on their front page! 1/8th mile in 3 seconds!!! Wow!!!)
Dale "Cork" Gindlesperger
-----Original Message-----
From: mapics-l-bounces@xxxxxxxxxxxx [mailto:mapics-l-bounces@xxxxxxxxxxxx] On Behalf Of Tom E Stieger
Sent: Tuesday, October 28, 2008 10:52 AM
To: mapics-l@xxxxxxxxxxxx
Subject: Re: [MAPICS-L] MRP Puzzler...
A couple of questions:
1. Why did you change the quantity from 250 to 242 instead of just canceling the order/line item. If this line item is complete it should not be in the mbcdrep file. Unless the order has other line items open, which is probably the case. When you change the quantity to match was has been shipped the status changes on the release and line item, but the order/line item doesn't remove from the open files. Can you delete a line item on an order after it has had partial shipment when there are still other open line items on the order?
2. Why do we have to run the 'audit allocation' and 'audit location' and 'audit on order' at all? Shouldn't XA do this automatically when needed? Every once in a while we have a problem that shows up and this fixes it. It is very frustating to have to tell users do this and it will fix the problem without knowing the why.
3. I can't make it to the flogging, can you record it and put it on YouTube?
-Tom Stieger
Engineer
California Fine Wire
805-489-5144 x235
-----Original Message-----
From: mapics-l-bounces@xxxxxxxxxxxx
[mailto:mapics-l-bounces@xxxxxxxxxxxx]On Behalf Of Charley Simpson
Sent: Tuesday, October 28, 2008 6:57 AM
To: MAPICS ERP System Discussion
Subject: Re: [MAPICS-L] MRP Puzzler...
My apologies to this august list.
It was NOT a blanket line, just a regular CO line item. Quantity was originally 250, we shipped 242, reduced the order qty to 242 and cancelled the B/O. We were getting a planned order for the 8 on "backorder."
Last night I ran the 'audit allocation' and 'audit location' and 'audit on order' and then re-ran MRP and it seems to be calculating planned orders correctly now, but I still show 8 on back order in the CO line view in field "Backorder quantity" cdz902.
Thoughts?
Thanks and sorry for the misleading information; I will have my planner publicly flog me at high noon today.
Cheers!
Charley Simpson
Turbonetics Inc.
Phone: 805-581-0333
Direct: 805-426-3410
Fax: 805-581-2640
www.TurboneticsInc.com
www.eTurbochargers.com
________________________________
The information in this email is confidential and may be legally privileged. It is intended solely for the addressee. Access to this email by anyone else is unauthorized. If you are not the intended recipient, any disclosure, copying, distribution or any action taken or omitted to be taken in reliance on it, is prohibited and may be unlawful. If you are not the intended addressee please contact the sender and dispose of this e-mail.
_______________________________________________
This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
To post a message email: MAPICS-L@xxxxxxxxxxxx
To subscribe, unsubscribe, or change list options,
visit:
http://lists.midrange.com/mailman/listinfo/mapics-l
or email: MAPICS-L-request@xxxxxxxxxxxx
Before posting, please take a moment to review the archives
at
http://archive.midrange.com/mapics-l.
As an Amazon Associate we earn from qualifying purchases.