  Mark,

  Yes,  I did find it. Thanks.

    ----------------------------------------------------------------------

    From:  "Turpin, Mark" <Mark.Turpin@xxxxxxxxx>
    Reply-To:  MAPICS ERP System Discussion <mapics-l@xxxxxxxxxxxx>
    To:  "MAPICS ERP System Discussion" <mapics-l@xxxxxxxxxxxx>
    Subject:  Re: [MAPICS-L] cell scheduling
    Date:  Tue, 13 Jun 2006 08:31:53 -0400
    Jeff,

    Have you looked at the Crew Clocking transaction in PMC?  This allows
    for labor time to be calculated with machine time only being calculated
    for the crew leader.

    Refer to the PMC user's Guide for additional information.

    Thanks

    Mark Turpin | XA Product Development, DG| Infor | office: 678-319-8019 |
    fax: 678-319-9019 | mark.turpin@xxxxxxxxx

    -----Original Message-----
    From: mapics-l-bounces@xxxxxxxxxxxx
    [mailto:mapics-l-bounces@xxxxxxxxxxxx] On Behalf Of Jeff Snyder
    Sent: Monday, June 12, 2006 10:34 AM
    To: mapics-l@xxxxxxxxxxxx
    Subject: [MAPICS-L] cell scheduling

        We have several work cells where we will have multiple folks clocked
    onto
        a single Shop packets, orders.  And we are trying to schedule with
    PCC and
        resolve overloads with CRP.

        Example:  3 employees clock onto a job at 7 am and off at 9 am.

        This would accumulate 6 hrs of labor - and this is fine and reflects
        reality.

        The problem is the JOB also accumulates 6 hrs of machine time -  2
    hrs per
        person.

        I need to be able to use machine hrs to schedule the cell - but the
    JOB
        will only take 2 hrs.

        Anytime we have more then 1 person on a packet the machine hrs are
        inflated.

        This in turn inflates our averages and later standards .

        I was curious if others out there have solved this 'cellular'
    scheduling
        issue.

        Any relief in PLMC, or rel 7 ?

        I appreciate any input

        Thanks

        Jeff Snyder,  CPIM
        Guide Technologies ( working on an issue for Betts Ind)

    _______________________________________________
    This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
    To post a message email: MAPICS-L@xxxxxxxxxxxx
    To subscribe, unsubscribe, or change list options,
    visit: http://lists.midrange.com/mailman/listinfo/mapics-l
    or email: MAPICS-L-request@xxxxxxxxxxxx
    Before posting, please take a moment to review the archives
    at http://archive.midrange.com/mapics-l.

    _______________________________________________
    This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
    To post a message email: MAPICS-L@xxxxxxxxxxxx
    To subscribe, unsubscribe, or change list options,
    visit: http://lists.midrange.com/mailman/listinfo/mapics-l
    or email: MAPICS-L-request@xxxxxxxxxxxx
    Before posting, please take a moment to review the archives
    at http://archive.midrange.com/mapics-l.

As an Amazon Associate we earn from qualifying purchases.

This thread ...

Replies:

Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.