Hello All. I know this is a basic question, but I am perplexed. How do you get the materials for a MO to be scheduled so that when the operation steps is scheduled to start, the need materials are due? Right now, If I cut a MO today and a due date a couple of months out, all the materials are required today, when I don't need the materials until the operations are due to start. Which module will schedule materials to coincide with the operations schedule? Thanks Weston Wheat Information Systems Manager Quality Thermistor Inc wwheat@xxxxxxxxxxxxxx www.thermistor.com
As an Amazon Associate we earn from qualifying purchases.
This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].