Hi All,

Thanks for your inputs to my query. but still we have issue here..

But we have checked cumulative yeild in ITEMASB file...the value was set to
1.00. even the Cost technique code for this item is 'R'.

we have checked Routing & work center file...there are hours in Run Labor in
both files.

Actually USER is expecting value in this feild ie "Std. Labor This level" &
"Current labor this level" in ITEMASB file.

Its happening some of the Catalogs but not all of them...Here is the
Additional information Regarding this issue :

The Operation Status of this catalogs is "10"
The Item type is 1 and also Cost flag was set to "B"
Current Cost status is set to "T"
Std Cost status is set to "T"

Still we couldn't figure it out what was the cause...really appreciate your
help.

Regards
Shareen



-----Original Message-----
From: Lisa Weaver [mailto:lweaver@guidetechnologies.com]
Sent: Saturday, October 26, 2002 12:36 AM
To: mapics discussion board
Subject: re[2]: Labor is not Rolling up in PDM Module (Costing)


Check the cumulative yield.  It may be set to zero.



> [ Converted text/html to text/plain ]
Bill is right on - cost technique code is the most likely cause and inactive
operations are easy to miss.
Another place to check is the routing and facility (Work Center) files.
There
must be hours in the routing (labor, machine) and rates in the same places
(labor, machine) in the work center file (current or standard, depending on
what kind of costs you are calculating). Also note the overhead code
controls
the calculation of overhead based on labor or machine time or amount - or
not
at all.
Dave Turbide
dave@daveturbide.com
www.daveturbide.com[1]
From: "Bill Mongan" <bmongan@generac.com>
To: <mapics-l@midrange.com>
Subject: RE: Labor is not Rolling up in PDM Module (Costing)
Date: Fri, 25 Oct 2002 11:37:34 -0500
Reply-To: mapics-l@midrange.com
a couple of ideas (these have bit me in the past):
the cost technique code in item master must be in place and consistent with
how you cost labor and overhead. For example, we use routings. Even if a
routing exists for the part, the cost technique code in item master must be
"R". If not, the labor won't roll up.
in the routing itself, there is a field called operation status. The options
are 00-inactive or 10-active. It may look like a routing exists and that
labor should be rolling up, but if he operation status was somehow set to
00-inactive, no labor rolls up.
Hope this helps.
-----Original Message-----
From: mapics-l-admin@midrange.com [mailto:mapics-l-admin@midrange.com]On[2]
Behalf Of Nellutla, Shareen N (Indsys)
Sent: Friday, October 25, 2002 6:58 AM
To: mapics-l@midrange.com
Subject: Labor is not Rolling up in PDM Module (Costing)
Hi,
I have a problem with Labor is not Rolling up.
What are the possibilites that Labor is not rolling up, but Material Cost is
happening.
I have situation here where "The labor is rolling up at the part level, but
not in every case and not at the top or next level"
I will really appreciate if some one can give some input on this.
Regards
Shareen
Dave Turbide, CFPIM, CMfgE, CIRM
Market Analysis and Communication
883 Ocean Blvd
Hampton, NH 03842
phone(603) 926-1435
fax (603) 926-0862
www.daveturbide.com[3]

===References:===
  1. http://www.daveturbide.com/
  2. mailto:mapics-l-admin@midrange.com%5DOn
  3. http://www.daveturbide.com/

_______________________________________________
This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
To post a message email: MAPICS-L@midrange.com
To subscribe, unsubscribe, or change list options,
visit: http://lists.midrange.com/cgi-bin/listinfo/mapics-l
or email: MAPICS-L-request@midrange.com
Before posting, please take a moment to review the archives
at http://archive.midrange.com/mapics-l.


 <
_______________________________________________
This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
To post a message email: MAPICS-L@midrange.com
To subscribe, unsubscribe, or change list options,
visit: http://lists.midrange.com/cgi-bin/listinfo/mapics-l
or email: MAPICS-L-request@midrange.com
Before posting, please take a moment to review the archives
at http://archive.midrange.com/mapics-l.


"THIS E-MAIL MESSAGE ALONG WITH ANY ATTACHMENTS IS INTENDED ONLY FOR THE
ADDRESSEE and may contain confidential and privileged information.
If the reader of this message is not the intended recipient,
you are notified that any dissemination, distribution or copy of this
communication is strictly Prohibited.
If you have received this message by error, please notify us
immediately, return the original mail to the sender and delete the
message from your system."



As an Amazon Associate we earn from qualifying purchases.

This thread ...


Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.