Hello

For an item is there a way to set a buffer day which allows MRP to
incorporate a one day gap between the Start Date calculated for a Parent
Item and the corresponding Due Date of the component? We currently do not
utilise operation scheduling in PCC (due to a lack of detailed routings) and
a typical leadtime will be 2 or 3 days per BOM level. Relying on a component
to be available first thing in the morning on a start date, when the
leadtimes are relatively short, causes us problems for the management of the
subsequent material issuing to the parent item.

We have looked at the Leadtime Adjustment Factor but this seems a bit messy.

Is this a common problem or is our thinking misguided as to the
interpretation of the due date to start date relationship?

Best regards

Paul



As an Amazon Associate we earn from qualifying purchases.

This thread ...


Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.