Dear Axel If you are using MRP or MPSP you could load the orders as "firm planned" then they could be released from MRP using regular menu options. I think this would be the easiest. Another method raising the orders direct into IM would be to populate the batch file(s) that are updated by AMIM40 option 1 and then run IM Order Release with/without shop packet. Hope this is useful. Regards Bob Cull Business Analyst working at Sylvania Lighting International. In a message dated 3/5/02 7:35:15 Pacific Standard Time, niederquell@selkirk.de writes: << Hi group, i am looking for a easy way of uploading either M/Os into Mapics directly or upload sort of planned orders which i then can release to M/Os using standard menu options. Is anybody out there doing this (i. e. from an external planning system)??? Mit freundlichen Grüßen / Kind Regards Axel Niederquell / IT SELKIRK Schornsteintechnik GmbH Wiehler Str. 5 D-51545 Waldbröl Telefon +49 2291 84-210 Fax: +49 2291 84-133 niederquell@selkirk.de http://www.selkirk.de >>
As an Amazon Associate we earn from qualifying purchases.
This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].
Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.