BPCS version 4.05CD
Would like to know if anybody has an idea of how to use the facility
planning daily lead time rate but create multiple planned orders? We are
attempting to use the daily lead time as the daily capacity of the
finished good. The forecast is backing up the planned order to the
correct start date but we would like one planned order per day in order
to:
1) Space out the raw material planned orders, not all material is needed
on the first day of production
2) Create daily shop orders to dispatch to production
Any advice is appreciated.
Ramona Marshall
Analyst
Group Dekko, Inc.
mailto:ramona@xxxxxxxxx
Phone:(260) 599-3702
http://www.dekko.com
As an Amazon Associate we earn from qualifying purchases.
This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact
[javascript protected email address].
Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.