Do you have negative # in any of the lead time days or routingss math?
I changed the due date and firmed up a forecast, then did the regens.
I am looking at the dates on the End-Item vs the dates on one of the
sub-assemblies, and the system seems to have reversed the reschedule
dates??
Example:
Part Number Planned-Release-Date Planned-Due-Date
Resched-Date-From-MRP
sub-assy 2008/02/20 2008/02/24
2008/03/24
end-item 2008/03/25 2008/03/29
2008/02/29
Above is how the system looks after the regens.
Seems to be incorrect on the sub-assy part, or on the end-item - one of
them seems backwards to me??
Don F. Cavaiani
IT Manager
Amerequip Corp.
920-894-7063
"It's amazing what you can accomplish if you don't care who gets the
credit." Harry S. Truman
--
This is the BPCS ERP System (BPCS-L) mailing list
To post a message email: BPCS-L@xxxxxxxxxxxx
To subscribe, unsubscribe, or change list options,
visit:
http://lists.midrange.com/mailman/listinfo/bpcs-l
or email: BPCS-L-request@xxxxxxxxxxxx
Before posting, please take a moment to review the archives
at
http://archive.midrange.com/bpcs-l.
Delivered-To: macwheel99@xxxxxxxxxx
As an Amazon Associate we earn from qualifying purchases.