Tom,
The only thing I can think of for you to check is to make sure that you
don't have a Shipping Calendar (DRP150) setup that is in conflict
(specifying non-work days as ship dates) because BPCS will "realign" the
due dates of the DRP orders to conform to the closest "non-late" ship
date. Good Luck.
Frederick C. Davy, CPIM, PMP
Business Systems Analyst
Interface Solution, Inc.
Phone: (315) 592-8101
Fax: (315) 592-8481
e-mail: fcdavy@xxxxxxxxxxxx
"Molyneux, Tom" <TMolyneux@xxxxxxxxxxxxxx>
Sent by: bpcs-l-bounces+fcdavy=sealinfo.com@xxxxxxxxxxxx
11/16/2006 05:51 AM
Please respond to
SSA's BPCS ERP System <bpcs-l@xxxxxxxxxxxx>
To
<bpcs-l@xxxxxxxxxxxx>
cc
Subject
[BPCS-L] DRP Due Date Problem
We have a problem with DRP540 (Resupply Order Release) highlighting Due
Dates as non-working days that ARE working days and are set up on the
Shop Floor Calendars (FSC) as working days.
This seems to happen every so often. I seem to remember it also happened
about this time last year, so I guess it could have something to do with
the calendar for the new year, but I don't know what. I think our
operators moved the dates a day or two either way to get the DRP release
to work and the problem seemed to disappear.
Anyone any ideas ? We are on V6.00.04 release of BPCS
Tom Molyneux
National Oilwell Varco
Mono Pumps Limited
MIS Department
Tel. 0161 214 2142
Fax. 0161 214 2344
E:mail Tom.Molyneux@xxxxxxx
tmolyneux@xxxxxxxxxxxxxx
As an Amazon Associate we earn from qualifying purchases.
This mailing list archive is Copyright 1997-2025 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].
Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.