Two additional points on Master scheduled items. 1) They are the basis  for 
rough-cut capacity, that is they are the only ones populated with a bill of  
resources. 2) If you have MPS at the top and bottom of your structure with MRP  
items in between - you have to run MPS then MRP then MPS a second time to pick 
 up the requirements for the bottom level items. 
 
Regards,
Larry Costain

As an Amazon Associate we earn from qualifying purchases.

This thread ...

Follow-Ups:

Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.