Two additional points on Master scheduled items. 1) They are the basis for rough-cut capacity, that is they are the only ones populated with a bill of resources. 2) If you have MPS at the top and bottom of your structure with MRP items in between - you have to run MPS then MRP then MPS a second time to pick up the requirements for the bottom level items. Regards, Larry Costain
As an Amazon Associate we earn from qualifying purchases.
This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].