Two additional points on Master scheduled items. 1) They are the basis for rough-cut capacity, that is they are the only ones populated with a bill of resources. 2) If you have MPS at the top and bottom of your structure with MRP items in between - you have to run MPS then MRP then MPS a second time to pick up the requirements for the bottom level items. Regards, Larry Costain
This mailing list archive is Copyright 1997-2026 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].