Hi,

If after running CRP (Capacity Reqmnt. Planning), it is found that, the 
capacity is insufficient to take care of the planned orders i.e. overloaded 
plan, there are 2 ways, either to reduce order Qty. or off-load (sub-contract) 
the job or do overtime. 
However, if off-loading can't be done due to some reason, is there any 
mechanism in BPCS that will automatically correct the customer order Qty. 
taking into consideration capacity constraint ?
or is it only in the form of messages to 'Expedite' the planned order or how is 
it ?

regards,
Prashanth

As an Amazon Associate we earn from qualifying purchases.

This thread ...


Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.