In BPCS (version 4.05 CD), do the routings operations get compressed for
a job that is past due?

 

For example:

I have a job that should have been released on 8/23 and I can release it
today, 8/30.

The routing are is follows:



 

Will BPCS ignore the move and queue times and compress them to zero?
Will it compress actual run times as well?

 

For MRP systems I have used before, move and queue times could be set at
an estimated and minimum move and queue time.  The estimated time was
used to plan orders under 'normal' circumstances and the minimum was the
hard constraint when these times were compressed due to an order being
late.  Run time was also a hard constraint that could not be violated.

 

Any help would be appreciated.sign me a BPCS novice.

 

Marc Graff

Production Control Manager

States Industries, Inc.

(541) 688-7871 ext. 283

 


As an Amazon Associate we earn from qualifying purchases.

This thread ...


Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.