We are looking for some advice on our BPCS V6.1.01 MRP/MPS setup.

We have a safety stock set as a minimum balance in MRP140 for a 
manufactured parent, but during planning the purchased child does not 
appear to take into consideration the lead time of both the parent and 
child. As a result the planned orders always have an expedite message 
attached to them.

In addition, we would like to distinguish between orders planned to meet 
customer requirements vs. those planned to meet minimum balance 
requirements.

Is there some specific setup that we need to follow to get this to work?

Any advise would be appreciated.

Thanks.

Doug McLauchlan

As an Amazon Associate we earn from qualifying purchases.

This thread ...


Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.