|
Santa, We are on 6.04, mixed mode and we have used queue days & move days in our routings. The move days is the amount of time you want to have after you complete the job (say to move parts). The hitch is that you need to open your shop orders by backward scheduling for it to pick up move days. Normally the queue days is the number of days that it takes before you run a job - if you need a couple of days to prepare to run the job then use queue days. As we generally backward schedule all of ours are set up for move days - I don't remember if the queue days is used when you forward schedule only - it may be included in the backward scheduling also. The actual run time is what you have set up using the basis code (which you can set up by hours per piece, or pieces per hour, the help text is great for this area if you are unsure of which to use.) This value is the machine or labor time it takes to actually run a part. Don't forget that when you open the shop order the due dates/start dates are calculated based on the capacity of the work center (do you have 1 shift for 8 hours available?, or 2 shifts for a total of 16 hours? do you have multiple machines tied to a work center?, do you have a work center effiecency of 80%? also make sure that your work center loading codes are set up for the type of hours you have in the routing machine or labor hours, etc.) For simplicity sake take the following example: If you set up with 2 days in queue time, and your standard run time is 100 pieces per hour, and your workcenter is available for 8 hours. When you open up the shop order (forward schedule) for 1000 pieces. The due date will be 4 days from the start date, 2 days to get it ready and 10 hours to run. If you set up the same part with 2 days in move time then you will get the same if you backward schedule - but your due date will be what you assign with the system assigning the start date 4 days earlier. We have not gotten sophisticated enough here to use the negative values in our routings so I am not an expert. So the following being in theory only...If you have more than one operation - you can use a negative value in the move/queue days (backward vs forward scheduling)to overlap the operations. In the above example - if you want to start the second operation after completing the first 100 pieces at the first operation - then set the move days on the first operation to -0.875 - "in theory" you are telling the system to move the parts after the first hour of run time if you backward schedule. Word of caution - Whatever number of days you use in the routing should match the lead time days for the MRP planning record (CIC file). The routing run times (pcs per hour, hours per pcs) should match the MRP daily lead time rate. This way the system does not 'knee jerk' rescheduled dates and due dates on lower level components once the shop order is opened. Good luck Beth A. Norris Production Control Manager Fawn Engineering Des Moines, IA bnorris@wittern.com -----Original Message----- From: Santa Rusli [mailto:srusli313@plasa.com] Sent: Tuesday, December 18, 2001 8:52 AM To: bpcs-l@midrange.com Subject: Re: Overlapping Operations days Mac, Thanks for that comprehensive explanation, Mc. Hail to the BPCS Guru!! :) Just to clarify things - the hours set up in the routings, do they actually affect the number of days a shop order will take? Last time, I tried this - inputing extreme hours to the machine / labor in a routing. Eg. 5000 hours in one operation to create a batch of Prod. A. Amazingly, when I created the shop order, the shop order still take one day to finish. This is really strange. That's why I thought shop order days are calculated only by move days / queue days. Is this because it only has one operation? Is this the right concept? Or should the shop order take [5000 / (available hours per day)] days to create a batch of Prod. A? So, when I input queue days, it should be -ve[5000 / (available hours per day)] in the next operation to have concurrent operations. But the end result is that the shop order will never be finished in one day right? Because the second operation cannot finish before the first operation is done. How should I report the inconsistency in the number of days a shop order will take? During labor ticket processing? I probably should try this at the office when it opens again. Hope you can shed a little bit more light at my direction in the meanwhile. Once again, thanks. Regards, Santa _______________________________________________ This is the SSA's BPCS ERP System (BPCS-L) mailing list To post a message email: BPCS-L@midrange.com To subscribe, unsubscribe, or change list options, visit: http://lists.midrange.com/cgi-bin/listinfo/bpcs-l or email: BPCS-L-request@midrange.com Before posting, please take a moment to review the archives at http://archive.midrange.com/bpcs-l.
As an Amazon Associate we earn from qualifying purchases.
This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].
Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.