Mike,
I have done a bunch, and they have all gone really smooth. When you
go from V5R4 to 7.1, you should read the memo to users for both releases
(6.1 & 7.1), and make sure you run ANZOBJCVN to figure out what application
programs won't convert. In addition, you need to make sure you have the
minimum release of your FSP firmware (for the release you are going to)
permanently applied before the upgrade, check out the informational APARs
for the release, as you need to get the PTFs required for the upgrade
(Database Cross Reference PTFs, Image Catalogue PTFs, and upgrade PTFs).
Insure you have the latest release for the I_BASE_01 so that it will make
the upgrade quicker, and the PTF installation quicker. If you are running
WAS, Domino, JAVA, or MQ make sure you verify the releases that will work
with 7.1, as there are many issues with having the right release.
By the way, I am doing a webcast with IBM next Tuesday on upgrading
to IBM i 7.1. On Tuesday February 8, 2011 from 2pm Eastern time IBM is
having a webcast on "Upgrading your IBM i" . You can register for the
presentation at the link below. Guy Paradise, World Wide IBM i Marketing
Manager will highlight and summarize all the IBM i offerings delivered in
2010 and their value. Mark Olson, IBM Power Systems World Wide Product
Manager will cover some of the technical details of moving up to the latest
hardware. Steve Will Chief Architect: IBM i Operating System will cover
the value of IBM i and new features & functions of 7.1. Pete Massiello of
iTech Solutions will cover real world experiences in moving clients up to
the latest Hardware & Operating System levels (6.1 & 7.1). To Register -
https://event.on24.com/eventRegistration/EventLobbyServlet?target=registrati
on.jsp&eventid=279216&sessionid=1&key=B15996E80A6C68E2FA300C22885500C9&partn
erref=mminstallaix&sourcepage=register<https://event.on24.com/eventRegistration/EventLobbyServlet?target=registrati%0Aon.jsp&eventid=279216&sessionid=1&key=B15996E80A6C68E2FA300C22885500C9&partn%0Aerref=mminstallaix&sourcepage=register>
I hope this helps,
Pete
--
Pete Massiello
iTech Solutions
http://www.itechsol.com
Add iTech Solutions on Facebook:
http://www.facebook.com/group.php?gid=126431824120
Add iTech Solutions on LinkedIn:
http://www.linkedin.com/groups?gid=2206093
iTech Solutions because IBM i (AS/400s) didn't come with System
Administrators
-----Original Message-----
From: midrange-l-bounces@xxxxxxxxxxxx
[mailto:midrange-l-bounces@xxxxxxxxxxxx] On Behalf Of Mike Cunningham
Sent: Monday, January 31, 2011 4:15 PM
To: Midrange Systems Technical Discussion
Subject: Upgrade V5R4 top V7R1
We have finally moved off the software application that we had that was
stuck at V5R4 and are going to start planning on getting current on V7R1.
We
are aware of all the things that went along with V6R1 upgrade and will be
running those scans again. We will get the "What's New" documents from IBM.
Has anyone done a V5R4 to V7R1 upgrade and have any tips to share that are
not documented? Out timeline is to do this in May/June 2011 timeframe
Thanks
--
--
This is the Midrange Systems Technical Discussion (MIDRANGE-L) mailing list
To post a message email: MIDRANGE-L@xxxxxxxxxxxx
To subscribe, unsubscribe, or change list options,
visit: http://lists.midrange.com/mailman/listinfo/midrange-l
or email: MIDRANGE-L-request@xxxxxxxxxxxx
Before posting, please take a moment to review the archives
at http://archive.midrange.com/midrange-l.
As an Amazon Associate we earn from qualifying purchases.
This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].
Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.