Thanks all.
Especially to Dave Turbide for the generous offer below, and to Mike Taylor @ Cistech for an implementation plan!
 
Regards...james
James LeLeux
IT Director: Cherry, Shur-Lok, & SPS Santa Ana
1224 East Warner Avenue
Santa Ana, CA 92705
M   714-929-8063
jleleux@xxxxxxxxxxx
-----Original Message-----
From: mapics-l-bounces@xxxxxxxxxxxx [mailto:mapics-l-bounces@xxxxxxxxxxxx] On Behalf Of Dave Turbide
Sent: Tuesday, January 11, 2011 5:24 AM
To: mapics-l@xxxxxxxxxxxx
Subject: Re: [MAPICS-L] Implementing Standard Costing
I'm on vacation this week so only checking email once a day. I'd be happy to chat with you about converting to standard costing. 
In addition to setting the interfaces, you'll need to decide on a number of procedural issues including how "standard" you want to be. MAPICS gives you a number of choices in tailoring and there are procedures you'll want to set up to gather the information and get it posted in the right places. 
I usually don't recommend automatic posting to G/L of everything that MAPICS is capable of doing - there are some variance calculations that are better done manually, in most cases. That said, the G/L interface can gather a lot of data for you that you can manually post and/or use to validate info that you gather in other ways so it makes sense to "activate" even if you aren't going to automatically post.
Anyway, if you can wait a couple days I'd be happy to spend some time with you on the phone next week. If there's something critical, drop me an email directly at dave@xxxxxxxxxxxxxxx with your phone number and I'll call you.
Dave Turbide
CSCP, CFPIM, CMfgE, CIRM
dave@xxxxxxxxxxxxxxx
office: (603) 964-6903
cell: (603) 401-0192
Website: www.daveturbide.com
 
 
Mon, 10 Jan 2011 17:35:41 -0500
from: "LeLeux, James" <jleleux@xxxxxxxxxxx>
subject: [MAPICS-L] FW: Implementing Standard Costing
Happy New Year all!
I am looking at implementing standard costing (XA R6) and was curious if
anyone knew of any guides from Infor or other sources to assist.
I see that we need to re-tailor from Actual to Standard (what will that
impact?). We currently use actual costing, but it is well structured outside
of MAPICS.
And not sure about this other PCC question currently set to NO:
C17 DO YOU WANT TO HAVE GENERAL LEDGER DISTRIBUTION?
Do the Router Variance (RV), Purchasing Variance (PV), and Material Usage
Variance (MUV) reports come out of AMC530 (Order closeout and purge)?
Are there any practical guides to the parameters for AMC530 as well as cost
roll-ups?
I did search the ML, but it was very issue specific, and I'm still at the
10,000 foot level.
Thanks in advance for any direction you may provide!
Looks like we have all out interfaces on except one:
           ENTER INTERFACE SELECTION:  1 - DEACTIVATE
                                       2 - ACTIVATE
 SEL  FROM APPLICATION                     TO APPLICATION
  2  Accounting Mgmt Accounts Payable     Accounting Mgmt General Ledger
2          Accounting Mgmt Accounts Payable     Inventory Management
  2  Accounting Mgmt Accounts Payable     Production Control and Costing
  1  Accounting Mgmt Accounts Receivable  Accounting Mgmt Accounts Payable
  2  Accounting Mgmt Accounts Receivable  Accounting Mgmt General Ledger
  2  Customer Order Management            Accounting Mgmt Accounts
Receivable
  2  Customer Order Management            Master Production Schedule
Planning
  2  Customer Order Management            Material Requirements Planning
  2  Inventory Management                 Customer Order Management
  2  Inventory Management                 Material Requirements Planning
  2  Inventory Management                 Product Data Management
  2  Inventory Management                 Production Control and Costing
  2  Master Production Schedule Planning  Material Requirements Planning
  2  Material Requirements Planning       Inventory Management
  2  Material Requirements Planning       Product Data Management
  2  Payroll                              Accounting Mgmt General Ledger
  2  Payroll                              Production Control and Costing
  2  Product Data Management              Inventory Management
  2  Product Data Management              Material Requirements Planning
  2  Production Monitoring and Control    Inventory Management
  2  Production Monitoring and Control    Payroll
  2  Production Monitoring and Control    Production Control and Costing
  2  Purchasing                           Material Requirements Planning
James LeLeux
IT Director: Cherry, Shur-Lok, & SPS Santa Ana
1224 East Warner Avenue
Santa Ana, CA 92705
M   714-929-8063
jleleux@xxxxxxxxxxx<mailto:jleleux@xxxxxxxxxxxxxx>
********
_______________________________________________
This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
To post a message email: MAPICS-L@xxxxxxxxxxxx
To subscribe, unsubscribe, or change list options,
visit: 
http://lists.midrange.com/mailman/listinfo/mapics-l
or email: MAPICS-L-request@xxxxxxxxxxxx
Before posting, please take a moment to review the archives
at 
http://archive.midrange.com/mapics-l.
As an Amazon Associate we earn from qualifying purchases.