Jeff:

One approach used by some MAPICS users is to implement Systems Plus' OTTO 
(On Time Orders).  OTTO has a scheduling function that performs three tasks:
1. Sequence the load based on some material characteristics - gauge, width, 
   material (steel vs. aluminum vs. copper vs. etc.), etc.
2. Present the load imposed on each work center and/or department by 
   customer demand.
3. Allow the shop supervisors to manipulate the shop order sequence based on

   load or resource availability.

For further information please contact me off line.


Roy Luce

Systems Plus - Midwest

Direct: 847-540-9635
        800-913-7587
Cell:   847-910-0884
Fax:    847-620-2799
Email:  rluce@xxxxxxxxxxxxxxxxxxx


-----Original Message-----
From: mapics-l-bounces@xxxxxxxxxxxx [mailto:mapics-l-bounces@xxxxxxxxxxxx]
On Behalf Of Jeff Snyder
Sent: Monday, December 04, 2006 1:18 PM
To: mapics-l@xxxxxxxxxxxx
Subject: [MAPICS-L] capacity vs Load analysis

   Hey Group.
    
   Here we are running MRP and using CRP to validate the build plan,  is it
   executable ?
    
   We have several Dept. where  the resources , labor are spread over
   multiple WCs.
    
   To add variable capacity records to maintain vacation or know 'off time'
   would be way to arduous a task.  Before we automate this process of
   loading these records I was wondering what some of you out there are
using
   to validate the MPS , and or Build plan after MRP generation.  Do you use
   an average, or try to nut the vacations to get as accurate a picture as
   possible.  Also as a follow up how do you manage the day to day manpower
   requirements?
    
   We have Browsersized our CRP output files and had envisioned having the
   dept Supv be able to perform an analysis of overloaded WCs in his dept,
   and use various views, subsets to check for available manpower elsewhere.
   We do not have or use MPSP, we have a PC based FCST system feeding MLI
   requirements directly to MRP. So,  Im not discussing the theroy of 'rough
   cut' capacity planning,  but rather is the generated build plan
executable
   ?
    
   We are also using PCC and the worklist,  but it seems to be awful time
   consuming for the dept. Supv. to shuffle the MOs to be sure all are
   completed on time.
    
    
   Any input on MPS generated Build plan Validation methods and Manpower
   management would be appreciated.
    
   Thanks
    
   Jeff Snyder, CPIM
   Guide Technologies, LLC
    
    
    
    
    
    

     ----------------------------------------------------------------------

   Stay up-to-date with your friends through the Windows Live Spaces friends
   list.
_______________________________________________
This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
To post a message email: MAPICS-L@xxxxxxxxxxxx
To subscribe, unsubscribe, or change list options,
visit: http://lists.midrange.com/mailman/listinfo/mapics-l
or email: MAPICS-L-request@xxxxxxxxxxxx
Before posting, please take a moment to review the archives
at http://archive.midrange.com/mapics-l.




As an Amazon Associate we earn from qualifying purchases.

This thread ...

Replies:

Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.