Jeff:
You might want to check into Systems Plus's OTTO (www.ottorpm.com). One of
the package's many functions is a Master Schedule Summary query that reports
the Demand versus Supply for Master Scheduled items over a 10 week period.
For example:
PAST
ITEM DESCRIPTION BOH DUE 11/15 11/22 11/29 12/06 12/13
12/20 12/27 01/03 01/10 TOTAL
0113003 DEMAND 25 25
14 2 2 68
SUPPLY 25 26
14 65
0213653 DEMAND 8 56
6 70
SUPPLY 8 56
64
0231132 DEMAND 2 2 2
5 11
SUPPLY 1 1 2 2 5
The query, and its available report, can be all Master Scheduled items, a
family of items, a range or even items based on a number of criteria.
Because OTTO is driven by sales orders everything you are trying to
accomplish, and substantially more, is supported by OTTO. In your client's
case they'd probably select a family and explode down just one level,
providing sales the information they need at the item level.
If you'll contact me off list I will send you some real-life examples of
the report from a few OTTO users - this list strips attachments.
Or you can read more about OTTO's underlying concept, Rapid Priority
Management (RPM), in Carol Ptak's book "ERP Tools, Techniques and
Applications for Integrating the Supply Chain; Second Edition" - the
discussion starts on page 188.
Roy Luce
Systems Plus
Main: 847-540-9635
Cell: 847-910-0884
Fax: 208-330-9032
Email: lwl@xxxxxxxxxxxxx
-----Original Message-----
From: mapics-l-bounces@xxxxxxxxxxxx [mailto:mapics-l-bounces@xxxxxxxxxxxx]On
Behalf Of Jeff Snyder
Sent: Monday, August 16, 2004 2:38 PM
To: mapics-l@xxxxxxxxxxxx
Subject: master scheduling - aggregate
Hey Group
I have a customer who can determine an aggregate volume of a family to be
produced, but can not determine the family part number breakdown.
They may have hundreds of part numbers in a family, and can only produce
say 400 a month of the entire family. They cannot master schedule to the
individual part number, would never guess the right mix. Nor will
percentages work 'i.e. planning bills.
They do not schedule any production,or purchasing activities until the
customer order is in hand, i.e. the customer order is quoted outside of
std CMLT.
The question, concern is how to stop sales from overbooking the
'aggregate
volume' for a family of final assembly parts ?
In the above example of 400 a month, they would like sales to have the
visibility of knowing what was booked on all sales orders for any item
participating in that family so they will not over commit the 400 a
month. They would like the sales rep to be able to perform the ATP on
the
phone, to insure a good promise date, but not based on the part number,
but aggregate demand compared to aggregate schedule for that family of
parts.
Has anyone written any such code, or is there a 3rd party pkg available.
Otherwise we will probably write something. Just wanted to check first.
Thanks for your attention, and look fwd to your input.
Jeff Snyder, CPIM
Mapics Consultant
_______________________________________________
This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
To post a message email: MAPICS-L@xxxxxxxxxxxx
To subscribe, unsubscribe, or change list options,
visit: http://lists.midrange.com/mailman/listinfo/mapics-l
or email: MAPICS-L-request@xxxxxxxxxxxx
Before posting, please take a moment to review the archives
at http://archive.midrange.com/mapics-l.
As an Amazon Associate we earn from qualifying purchases.
This mailing list archive is Copyright 1997-2025 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].
Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.