Don,
I'm going from memory here since we are on 6.004 but there may be a Daily
Lead Time rate in MRP140 in 4.05 CD as well. If so, you can enter a value
in this field that will be the equivalent of the amount of the product
that can be produced in a given day, include any move, queue, or run time.
When you do this it will look at the planned order, and based on the DLTR,
it will calculate a more accurate start and end date for the planned
order. It is still going to utilize the request or release dates you are
using but the end result should be much more accurate than a standard
planned order.
Robert A. Brown, CPIM
BPCS System Manager
Interface Solutions Inc.
Phone:(315) 592-8136
email: rabrown@xxxxxxxxxxxx
From:
bpcs-l-request@xxxxxxxxxxxx
To:
bpcs-l@xxxxxxxxxxxx
Date:
10/01/2009 07:40 AM
Subject:
BPCS-L Digest, Vol 7, Issue 148
Sent by:
bpcs-l-bounces+rabrown=sealinfo.com@xxxxxxxxxxxx
Send BPCS-L mailing list submissions to
bpcs-l@xxxxxxxxxxxx
To subscribe or unsubscribe via the World Wide Web, visit
http://lists.midrange.com/mailman/listinfo/bpcs-l
or, via email, send a message with subject or body 'help' to
bpcs-l-request@xxxxxxxxxxxx
You can reach the person managing the list at
bpcs-l-owner@xxxxxxxxxxxx
When replying, please edit your Subject line so it is more specific
than "Re: Contents of BPCS-L digest..."
*** NOTE: When replying to this digest message, PLEASE remove all text
unrelated to your reply and change the subject line so it is meaningful.
Today's Topics:
1. 405cd - Start dates change? (Don Cavaiani)
2. Re: 405cd - Start dates change? (Dania Percival (IBF))
3. Re: 405cd - Start dates change? (Don Cavaiani)
4. Re: Power6 520 system upgrade (Alejandro Piliado)
5. Re: 405cd - Start dates change? (Kent Vanhorn)
6. Re: 405cd - Start dates change? (Don Cavaiani)
7. Re: Power6 520 system upgrade (Renato Konda)
8. Guidelines for BPCS-L mailing list (mailman@xxxxxxxxxxxx)
----------------------------------------------------------------------
message: 1
date: Wed, 30 Sep 2009 14:28:12 -0500
from: "Don Cavaiani" <dcavaiani@xxxxxxxxxxxxx>
subject: [BPCS-L] 405cd - Start dates change?
Confusion:
I enter a forecast and run mps
I run mrp and cap
I have a planned order with a start date
Then, I release that planned order to a shop oder, and the start date
rolls "back".
What is the logic causing that start date to change - on the shop order?
TIA,
Don C.
Don F. Cavaiani
IT Manager
Amerequip Corp.
920-894-7063
"It's amazing what you can accomplish if you don't care who gets the
credit." Harry S. Truman
------------------------------
message: 2
date: Wed, 30 Sep 2009 15:56:40 -0400
from: "Dania Percival (IBF)" <dpercival@xxxxxxxxxxxxx>
subject: Re: [BPCS-L] 405cd - Start dates change?
Check your shop calendar
----- Original Message -----
From: bpcs-l-bounces+dpercival=interbake.com@xxxxxxxxxxxx
<bpcs-l-bounces+dpercival=interbake.com@xxxxxxxxxxxx>
To: bpcs-l@xxxxxxxxxxxx <bpcs-l@xxxxxxxxxxxx>
Sent: Wed Sep 30 15:28:12 2009
Subject: [BPCS-L] 405cd - Start dates change?
Confusion:
I enter a forecast and run mps
I run mrp and cap
I have a planned order with a start date
Then, I release that planned order to a shop oder, and the start date
rolls "back".
What is the logic causing that start date to change - on the shop order?
TIA,
Don C.
Don F. Cavaiani
IT Manager
Amerequip Corp.
920-894-7063
"It's amazing what you can accomplish if you don't care who gets the
credit." Harry S. Truman