Found this on einfo, hope it helps to explain your message:
 
 
cause: EAM3254 ACTION IS NOT VALID - ORDER STATUS IS 45, when attempting to 
select an order for closeout

fix: To get a Manufacturing Order to a status 55, you must complete it in both 
IM and PCC.  To complete the order in IM, an RM transaction with a 0 qty and 
completion code of C must be entered.  This will take the order from a 40 
(activity reported) to a 45 (material complete but labor not) or from a 50 
(labor complete but material not) to a 55 (material and labor complete).  Then, 
to complete the order in PCC, all operations must be at a status 40, 50 (if 
using move transactions, or 00 (inactive).  Then do an order complete 
transaction in PCC Shop Activity Update.  This will take an order from a 45 to 
a 55 or from a 40 to a 50.  Once both IM and PCC transactions have been 
completed, the order will be at a status 55.


        -----Original Message----- 
        From: mapics-l-bounces@xxxxxxxxxxxx on behalf of henny 
        Sent: Wed 9/15/2004 3:32 AM 
        To: MAPICS ERP System Discussion 
        Cc: 
        Subject: Manufacturing Order Status remains 45 after PCC completed
        
        

        Hi Group,
        
        I have one MO which status is 45 even after labor
        reporting is completed (OPSTC is 40 for all
        operations).
        
        The thing is when I tried to close the MO thru
        normal close, MAPICS gave me error message:
        E AM-3254 ACTION IS NOT VALID - ORDER STATUS IS 45
        
        My question are:
        1. What is the valid OSTAT that eligible for normal
           MO closing? Is it 50? I supposed 50 means PCC
           completed, IM not completed. For this MO, IM and
           PCC are already completed, so I don't think 50 is
           the correct status.
        
        2. Is the MO Closing can be automated somehow?
           I mean when IM and PCC are completed, can
           MAPICS automatically change the OSTAT to 55?
           If yes, what are the setup need to be done?
        
        Thanks in advance. Sorry, if this topic ever posted
        before.
        
        Sincerely,
        Henny.
        
        
        
                       
        __________________________________
        Do you Yahoo!?
        Yahoo! Mail - 50x more storage than other providers!
        http://promotions.yahoo.com/new_mail
        _______________________________________________
        This is the MAPICS ERP System Discussion (MAPICS-L) mailing list
        To post a message email: MAPICS-L@xxxxxxxxxxxx
        To subscribe, unsubscribe, or change list options,
        visit: http://lists.midrange.com/mailman/listinfo/mapics-l
        or email: MAPICS-L-request@xxxxxxxxxxxx
        Before posting, please take a moment to review the archives
        at http://archive.midrange.com/mapics-l.
        
        


As an Amazon Associate we earn from qualifying purchases.

This thread ...


Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.