You have several potential problems.
First is to get the planning working correctly.
Second is the impact on other things like Cost Roll-up if you have inappropriate Engineering data to the type of item.
We also have parts that fluctuate between being purchased and being manufactured, based on a number of factors, such as cost and speed with which we need something when we have a capacity problem. If you want to keep the BOM on the purchased item, I suggest you change the effectivity so that it is not to be currently paid attention to, then if you want to change it back to manufactured, then change the effectivity on BOM and Routings so that once again that data is to be included.
We also have an outsourcing scenario in which we changed the item # structure, so that the components sent to the outsourcer are tracked as discrete items, separate from the item made by the outsourcer.
We are 405 CD Mix Mode
-
Al Macintyre http://www.ryze.com/go/Al9Mac
Find BPCS Documentation Suppliers http://radio.weblogs.com/0107846/stories/2002/11/08/bpcsDocSources.html
BPCS/400 Computer Janitor at http://www.globalwiretechnologies.com/


The components CCC and DDD will still be planned even I change the item
type of assembly BBB to Purchased (N). Do I have to delete the structure
finally if we would like
to get the BBB be planned ?

Thanks.

Jingker Cheng

>Only change the item's Item type to purchase property. need not delete the
BOM.
>as a client requirement, the BOM may be a reference.>
>Ren
----- Original Message -----

> The problem is that you are oursourcing the item and making it a
component for the item type, but it still plans the sub components.

Delete the BOM and
> make sure that the item type has the flag set to mfg = No, so that it
will plan this as a purchased item.
>
> Have a great day.
>
> John Kasper
> J.D. Kasper & Associates, Inc.
> KASP6281@xxxxxxx
> (847) 644-1042 Cell Phone
Dear All:

Using BPCS C/S v6.1.01 on HP-UX. Have a question about the MRP calculating
result.

Product "AAA" with assembly "BBB" and the BBB with two components "CCC" and
"DDD".
Normally, the item type of BBB is assembly. After the MRP execution,
requirement
CCC and DDD will be calculated.

Question is:

If we oursourcing the BBB and change the item type to component, the
requirement CCC and
DDD will be still calculated in the same BOM structure. But we just needs
to calculate the
BBB only.

Can anyone know how to solve it ? Thanks.

Jingker Cheng



As an Amazon Associate we earn from qualifying purchases.

This thread ...

Replies:

Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.