Jingker-

        I get a sense that the outsourcing may be a temporary or
intermittent arrangement.  If this is the case, you not only have to address
two planning scenarios (production vs. purchased), but also two costing
scenarios.

        Assuming that both scenarios will exist, I would create a second
part number for the out-sourced BBB and set this up as an alternate item for
the produced BBB.  This second part would have no BOM. And with two separate
parts, you could cost by production costs or by purchase price.

        When associated with a separate Materials method code, that second
method would be selected to create the correct type of Shop Order, and then
the produced BBB could be planned for (materials and capacity) or the
out-sourced BBB could be purchased/transferred in.

JB

-----Original Message-----
From: JINGKER_CHENG@xxxxxxxxxxxx [mailto:JINGKER_CHENG@xxxxxxxxxxxx]
Sent: Wednesday, July 16, 2003 8:25 AM
To: bpcs-l@xxxxxxxxxxxx
Subject: Reply: MRP and BOM (Item type) setting


The components CCC and DDD will still be planned even I change the item
type of assembly BBB to Purchased (N). Do I have to delete the structure
finally if we would like
to get the BBB be planned ?

Thanks.

Jingker Cheng


>
>Only change the item's Item type to purchase property. need not delete the
BOM.
>as a client requirement, the BOM may be a reference.
>
>Ren
----- Original Message -----
From: <KASP6281@xxxxxxx>
To: <bpcs-l@xxxxxxxxxxxx>
Sent: Wednesday, July 16, 2003 12:57 AM
Subject: Re: MRP and BOM (Item type) setting


> The problem is that you are oursourcing the item and making it a
component
> for the item type, but it still plans the sub components.  Delete the BOM
and
> make sure that the item type has the flag set to mfg = No, so that it
will
> plan
> this as a purchased item.
>
> Have a great day.
>
> John Kasper
> J.D. Kasper & Associates, Inc.
> KASP6281@xxxxxxx
> (847) 644-1042 Cell Phone
Dear All:

Using BPCS C/S v6.1.01 on HP-UX. Have a question about the MRP calculating
result.

Product "AAA" with assembly "BBB" and the BBB with two components "CCC" and
"DDD".
Normally, the item type of BBB is assembly. After the MRP execution,
requirement
CCC and DDD will be calculated.

Question is:

If we oursourcing the BBB and change the item type to component, the
requirement CCC and
DDD will be still calculated in the same BOM structure. But we just needs
to calculate the
BBB only.

Can anyone know how to solve it ? Thanks.

Jingker Cheng




_______________________________________________
This is the SSA's BPCS ERP System (BPCS-L) mailing list
To post a message email: BPCS-L@xxxxxxxxxxxx
To subscribe, unsubscribe, or change list options,
visit: http://lists.midrange.com/mailman/listinfo/bpcs-l
or email: BPCS-L-request@xxxxxxxxxxxx
Before posting, please take a moment to review the archives
at http://archive.midrange.com/bpcs-l.

As an Amazon Associate we earn from qualifying purchases.

This thread ...


Follow On AppleNews
Return to Archive home page | Return to MIDRANGE.COM home page

This mailing list archive is Copyright 1997-2024 by midrange.com and David Gibbs as a compilation work. Use of the archive is restricted to research of a business or technical nature. Any other uses are prohibited. Full details are available on our policy page. If you have questions about this, please contact [javascript protected email address].

Operating expenses for this site are earned using the Amazon Associate program and Google Adsense.